That's strange, I ordered before you but scheduled in June...... But mine is Lariatchapman 11/15 hybrid order scheduled for 5/23 build week
https://www.mavericktruckclub.com/forum/threads/-maverick-scheduling-next-week-4-25-for-production-build-weeks-5-30-–-6-20.14029/post-278742
I emailed with them today, and they still had 7 remaining April allocations that have yet to be scheduled. 96 unscheduled hybrids, 85 unscheduled Ecoboosts (181, close enough to the number you got...I spoke to Chapman two days ago and they confirmed 182 unscheduled orders. I still think it's possible they're fulfilled.
For reference, I also have an order at Philly with Ed. Twin truck. That order is unscheduled/clean.
All other things being equal, because they are constrained on the hybrid powertrain, but not the Ecoboost powertrain. But if they are from different dealers, or different regions, allocations come into play as well. Tim has also mentioned that at times it seems they schedule one particulat powertrain and/or trim level in bunches, so maybe they were just in an Ecoboost phase at the time?I still want someone to explain to me why a December Lariat Lux Ecoboost would be scheduled before an October Lariat Lux Hybrid.
Tim alludes to this in all of his videos. Saying you *might* get pushed to 2023 if you ordered a fully loaded hybrid in October/Navember or if you ordered a fully loaded Ecoboost in December/early January.
I can't wrap my mind around that.
The other aspect is an Oct/Nov hybrid is the last in the queue of all the hybrids, whereas there were still a lot of EBs ordered after December. Further, Ford always expected to build way more EBs than Hybrids, so they likely have plenty of surplus EB parts available (even if it's Just in Time), since they over-ordered EB components and under-ordered hybrid components.All other things being equal, because they are constrained on the hybrid powertrain, but not the Ecoboost powertrain. But if they are from different dealers, or different regions, allocations come into play as well. Tim has also mentioned that at times it seems they schedule one particulat powertrain and/or trim level in bunches, so maybe they were just in an Ecoboost phase at the time?
Hmmm, hadn't thought about taking the train up there. I had planned to drive up with my son and have him drive the old car home. Might have to reconsider...My Nov 2 order for an EB XLT Lux DIBL CP360 AWD from Horsham was scheduled a few weeks ago for the week of 6/6. I was at Priority 2 for a few weeks before that. Ashlie has been great to check on its status for me every time I ask (about once a month). Now, I'm looking forward to a train ride up to Philly for a cheesesteak and a new truck!
Silly question, has Chapman released their allocation numbers yet? Silly because if you knew you would have posted. Just couldn’t stop myself from asking!Hmmm, hadn't thought about taking the train up there. I had planned to drive up with my son and have him drive the old car home. Might have to reconsider...
Congrats on getting your build date! I agree that Ashlie, Tom, and Kyle, & Steven have all been awesome in responding to my (excessive amount of) emails asking for updates on remaining unscheduled build counts, monthly allocations, etc.
They don’t have their May number yet.Silly question, has Chapman released their allocation numbers yet? Silly because if you knew you would have posted. Just couldn’t stop myself from asking!
Nice Tom Petty reference BTW!
Got the allocation for the "April cycle" from the team at Chapman-Horsham today, and was really dismayed to hear that it was only 29 (after hearing the huge jumps experienced by Granger & Long-McArthur for their April allocations, I was hoping for a similar bump for Chapman).
...
But I gotta have something to hope for...
Well, pure conjecture, but let's try. Last cycle, LongMcArtur had 85 allocated units to Chapman's 29. Current (May allocations) Long-McArthur numbers show 12 for July build -- not June. This seemed odd given roughly the same backlog and Chapman still appearing to have a front-ended (June/July/Aug) order profile relative to LM. So let's conjecture that LM received a two month allocation in April (similar to Chapman's Dec/Jan) vs Chapman's 29 for May builds.Looks like Long McArthur got only 12 allocations for May with 221 left to schedule.