Anyone in a similar situation? Or have information for me?
My truck (2024 Lariat) was scheduled for the week of 11/20, delayed to 11/27.
The pizza tracker switched to In progress on 11/30, the modules populated the same day, and then I received this email below yesterday.
The dealer tells me he can only see that my truck is still at the factory. Any insight is apprecaited!

Ford Maverick Delay after starting build... 1702053254233



Confirmed​
Scheduled
for Production​
Build in
Progress​
Shipped​




Your vehicle is almost built.

We understand it has been too long since you last heard from us. Just wanted to give you an update on the status of your Maverick Lariat order. While production of your vehicle was projected to begin the week of November 27, 2023, supply chain challenges continue to cause delays and uncertainty.
This is frustrating, we get it. We want nothing more than to get your Ford up on the line and start assembling it. And we will continue to work hard to reduce the delays to try to get you on the road in your new vehicle soon.
We’ll be sure to keep you updated as we get more information, at least once every 45 days. Hang in there. We really do appreciate your patience and understanding.​


Sponsored

 

vRS

Well-known member
Joined
Sep 15, 2022
Threads
0
Messages
177
Reaction score
187
Location
.
Vehicle(s)
None
Engine
Undecided
Yes build week 11/13 orders have been stuck in production for several weeks.
 

ndmiller

2.0L EcoBoost
Well-known member
First Name
Noah
Joined
Oct 20, 2023
Threads
4
Messages
248
Reaction score
237
Location
Atlanta
Vehicle(s)
2024 Maverick XLT Azure Blue Metallic
Engine
2.0L EcoBoost
Missing something for the truck build they thought would be there by now. It's not, so you're waiting and it's probably some external trim piece or otherwise stupid holding everything up.
 

Old Man

2.0L EcoBoost
Banned
Banned
First Name
Mike
Joined
Jan 6, 2023
Threads
6
Messages
1,332
Reaction score
1,731
Location
Nebraska
Vehicle(s)
2023 Lariat
Engine
2.0L EcoBoost
Build in progress/in production on the tracker can mean the order to build was sent to the factory up to 10 days before the actual build starts. During build they may have problems with a part and finish the build but park it until they have the part available or problem fixed. A year or two ago car manufacturers built cars but parked many of them until parts came in. As most dealers will tell you don't trust any date until the shipped date appears (but I've even seen some systems say it was delivered to dealer but was actually still sitting at the factory - Stellantis).
 
  • Like
Reactions: vRS

vRS

Well-known member
Joined
Sep 15, 2022
Threads
0
Messages
177
Reaction score
187
Location
.
Vehicle(s)
None
Engine
Undecided
Build in progress/in production on the tracker can mean the order to build was sent to the factory up to 10 days before the actual build starts. During build they may have problems with a part and finish the build but park it until they have the part available or problem fixed. A year or two ago car manufacturers built cars but parked many of them until parts came in. As most dealers will tell you don't trust any date until the shipped date appears (but I've even seen some systems say it was delivered to dealer but was actually still sitting at the factory - Stellantis).
It sounds like that this may be the case. They have built a bunch of Maverick's and they have been parked up while they wait for the missing parts to come in.

If they were completely built then the Ford tracker or Ford CS would be able to see the built status and it would be awaiting shipping.
 

Sponsored

DRICH2027

2.0L EcoBoost
Well-known member
First Name
David
Joined
Sep 4, 2023
Threads
22
Messages
117
Reaction score
43
Location
St Louis Missouri
Vehicle(s)
2024 Ford Maverick Lariat AWD
Engine
2.0L EcoBoost
Clubs
 
Anyone in a similar situation? Or have information for me?
My truck (2024 Lariat) was scheduled for the week of 11/20, delayed to 11/27.
The pizza tracker switched to In progress on 11/30, the modules populated the same day, and then I received this email below yesterday.
The dealer tells me he can only see that my truck is still at the factory. Any insight is apprecaited!

1702053254233.png


Confirmed​
Scheduled
for Production​
Build in
Progress​
Shipped​

Your vehicle is almost built.

We understand it has been too long since you last heard from us. Just wanted to give you an update on the status of your Maverick Lariat order. While production of your vehicle was projected to begin the week of November 27, 2023, supply chain challenges continue to cause delays and uncertainty.
This is frustrating, we get it. We want nothing more than to get your Ford up on the line and start assembling it. And we will continue to work hard to reduce the delays to try to get you on the road in your new vehicle soon.
We’ll be sure to keep you updated as we get more information, at least once every 45 days. Hang in there. We really do appreciate your patience and understanding.​
Got the same letter and have the same build. Call Ford Marking and they can actually see more than the sales manager. My Sales manger told me nothing and the marking department and they explained. Told me there were paint issue but the ETA was still the same for me. So Fingers crossed.
 
OP
OP
First Name
Bryan
Joined
Jan 18, 2023
Threads
2
Messages
7
Reaction score
1
Location
Virginia
Vehicle(s)
2008 Ford Ranger
Engine
2.5L Hybrid
Got the same letter and have the same build. Call Ford Marking and they can actually see more than the sales manager. My Sales manger told me nothing and the marking department and they explained. Told me there were paint issue but the ETA was still the same for me. So Fingers crossed.
Have your modules populated?
 

Mother Trucker

2.5L Hybrid
Active member
First Name
John
Joined
Oct 13, 2023
Threads
8
Messages
42
Reaction score
22
Location
Pennsylvania
Vehicle(s)
2024 Ford Maverick XLT
Engine
2.5L Hybrid
i was scheduled for the week of 11/20 for my 2024 XLT hybrid. Then I got the delay email on 11/30.
Ford Maverick Delay after starting build... IMG_0982

I checked with Ford chat when I got this and got this info from them.
I appreciate your patience! Your 2024 Maverick is in production with a secondary status of returned from body company. The vehicle has been returned from the body company (upfitter) and we are working hard to get it delivered! I see the vehicle's location as Ford Hermosillo Assembly, SO. The estimated time of arrival ranges from 12/18/23-12/24/23. Please kindly note that these dates are an estimate and are subject to change. You can track your vehicle through the process at https://shop.ford.com/vehicleordertracking#/ (https://shop.ford.com/vehicleordertracking#/) Please keep in contact with your dealer as they have the most updated information regarding order status.
I think on 12/1 I checked the modules and they were live.
My dealer said he has no additional info.
I checked today 12/7 on Ford chat and they said the only info they have on it now is that it’s in production.
The tracker hasn’t updated since 11/23.
Ford Maverick Delay after starting build... IMG_0983
Like most of you waiting on a maverick, I’m feeling impatient. Maybe more for me as I sold my Ranger when I got my build date. Me and my mustang are hoping to not see much snow here in PA before the maverick gets here.
 

Ozarkbeard

Well-known member
Joined
May 22, 2022
Threads
14
Messages
4,344
Reaction score
5,476
Location
.
Vehicle(s)
.
Engine
Undecided
i was scheduled for the week of 11/20 for my 2024 XLT hybrid. Then I got the delay email on 11/30.
IMG_0982.webp

I checked with Ford chat when I got this and got this info from them.

I think on 12/1 I checked the modules and they were live.
My dealer said he has no additional info.
I checked today 12/7 on Ford chat and they said the only info they have on it now is that it’s in production.
The tracker hasn’t updated since 11/23.
IMG_0983.webp
Like most of you waiting on a maverick, I’m feeling impatient. Maybe more for me as I sold my Ranger when I got my build date. Me and my mustang are hoping to not see much snow here in PA before the maverick gets here.
You are optimistic. My truck was ordered on 9/15/22, built 8/22/23 and shipped the next day, 8/23/23. It sat in the terminating rail yard for 3 weeks and didn't arrive at the dealer until 10/2/23. I hope your delay isn't as long.
 
Sponsored

KyleM

2.5L Hybrid
Active member
Joined
Mar 11, 2022
Threads
4
Messages
30
Reaction score
21
Location
Manhattan, KS
Vehicle(s)
None.
Engine
2.5L Hybrid
Can confirm, tracker is broken. Chat said vehicle is built and on its way but tracker says in production still.

Chat or phone call to get the most accurate information.
 

Heavyt100

2.0L EcoBoost
Member
First Name
Tom
Joined
Apr 5, 2023
Threads
1
Messages
23
Reaction score
18
Location
Southest
Vehicle(s)
F-150, Maverick on order
Engine
2.0L EcoBoost
Mine was also scheduled to be built week of 11/27. I got the same letter.
 

ilikebike

2.5L Hybrid
Well-known member
Joined
Feb 7, 2023
Threads
5
Messages
681
Reaction score
1,112
Location
SoCal
Vehicle(s)
2024 Ford Maverick Lariat Hybrid HPR w/ BAP
Engine
2.5L Hybrid
Can confirm, tracker is broken. Chat said vehicle is built and on its way but tracker says in production still.

Chat or phone call to get the most accurate information.
Did they specifically say it was shipped, or just that it was built and had an ETA to the dealer?
My dealer ETA has already come and gone and it's still just been built and waiting to ship.
 

Richard Deeds

2.5L Hybrid
New member
First Name
Rich
Joined
Nov 18, 2023
Threads
0
Messages
1
Reaction score
0
Location
Honey Brook Pa
Vehicle(s)
2024 Maverick
Engine
2.5L Hybrid
Got the same letter and have the same build. Call Ford Marking and they can actually see more than the sales manager. My Sales manger told me nothing and the marking department and they explained. Told me there were paint issue but the ETA was still the same for me. So Fingers crossed.
I got the same email. Mine was originally scheduled Nov 24, then moved to 27, and still there. My email was identical.
 

hdave

2.5L Hybrid
Well-known member
Joined
Jul 24, 2023
Threads
22
Messages
643
Reaction score
739
Location
Toronto, Canada
Vehicle(s)
'23 Alto Blue Maverick XLT
Engine
2.5L Hybrid
Mine started production 11/28 and chat told me the estimated build is now 1/16.
Probably another month or two after that to reach my dealer in the Toronto area.