Sponsored

Search results

  1. Latest Maverick Production Key Commodity Constraints + Total Retail Unscheduled Orders (9/25/23)

    There are currently 41,486 total retail unscheduled orders as of 9/25/23. Retail USOB: Is the current mix of retail orders in the unscheduled order bank (USOB) at the time the report was run. The report only looks at orders that are “clean”, meaning they do not have a compatibility error...
  2. Maverick Main Commit Scheduling This Week (9/21/23) for Production Weeks 11/06 - 11/27

    **Main commit is how many units were originally allocated for the week. In this case how many were allocated for build week 45. Example, I have 2 allocations for week 45. I will have 2 units scheduled on Thursday. Some dealers will have "revised" allocations for certain weeks. All the...
  3. Latest Maverick Production Key Commodity Constraints + Total Retail Unscheduled Orders (9/5/23)

    BTW all scheduling appears on hold. No info released this week. Note: There are currently 47,961 total retail unscheduled orders. Retail USOB: Is the current mix of retail orders in the unscheduled order bank (USOB) at the time the report was run. The report only looks at orders that are...
  4. Maverick Clean-Up Scheduling This Week (8/17/23) for Production Weeks 9/4 - 10/9

    **Dressing Period refers to the ability to modify certain options/features of orders input based on dealer commitment before they schedule (usually within commodity constraints) 2024MY Scheduling = TBD